Zone C Update 03/31/2020

4:05PM March 31, 2020

Contractors are currently working on drops to the customer homes in Area 1.  Priority is being placed on customers that were early backers at www.ElCampoFiber.com.  Construction for Area 1 should be completed this week.  Work on Area 2 (white shaded area) begins next week. Fiber splicing continues in Area 1 and customers should start being contacted for installs in mid-April.  Overall, the Zone C project is still on schedule.